Our Projects
EPC have successfully executed and delivered a number of key projects in various sectors, including mining and resources. Below are examples of the type of projects which have been successfully delivered.
Mine Ramp 32 Power
Supply Project
Project Brief
​
66/6.6kV power lines and Substation (SS) 38 to be relocated in order for mining operations to continue with the R32 pit.
Scope includes the installation of a new stubline extended from ABS 55 and relocation / upgrade of Substation 38.
Capital project - $2,1 M
Project Completion Dec 2012
Deliverables
​
Retraction of 3km of redundant 66/6.6kV Power lines
Installation of a new 700 meter long 66kV Stubline with underground road crossing and transportable mining substation earth mat.
Relocation of a fixed 66/6.6kV fixed substation including new concrete bund, earth mat and modifications to make the substation compliant to Australian standards.
Mine Transportable Mining Substation Upgrade Project
Project Brief
​
Project purpose is to install 66kV Circuit breakers and integrated arc flash protection including differential protection on 12 transportable mining substations.
Capital project - $7,5 M over 4 years
Project Completion Dec 2015
Deliverables
​
New 66kV ABB EDF SK1-1 2500A 72.5KV 25kA Circuit Breaker
New 72.5KV 100:1 Outdoor Current Transformers for over current and differential protection
New ABB RET615 Transformer Protection Relay with integrated arcflash relay
New Fortress interlocking system
Mine Ramp 16 Communications
Tower Project
Project Brief
​
The effectiveness of the existing Ramp 20 communications tower diminished with the advance of mining operations thus requiring the need for a new communications tower.
Capital project - $1,04 M
Project Completion Oct 2012
Deliverables
A new 60 meter communications tower
Improved radio and network communication along the mines haul road, back access road and northern pits.