Mine Ramp 32 Power Supply - BMA
Blackwater Mine
66/6.6kV power lines and Substation (SS) 38 to be relocated in order for mining operations to continue with the R32 pit.
Scope includes the installation of a new stubline extended from ABS 55 and relocation / upgrade of Substation 38.
Capital project - $2,1 M
Project Completion Dec 2012
Deliverables
​
Retraction of 3km of redundant 66/6.6kV Power lines
Installation of a new 700 meter long 66kV Stubline with underground road crossing and transportable mining substation earth mat.
Relocation of a fixed 66/6.6kV fixed substation including new concrete bund, earth mat and modifications to make the substation compliant to Australian standards.